TL;DR
Two grid-scale battery projects with a combined 125 MW / 265 MWh have entered operation in the Netherlands and Lithuania. Return’s 100 MW Antares facility is connected to TenneT’s 150 kV grid, while European Energy’s 25 MW battery is paired with a 78.5 MW solar farm in Anykščiai.
Two large-scale battery projects totaling 125 MW of power capacity and 265 MWh of storage have entered operation in the Netherlands and Lithuania, adding grid-connected storage at a time when the Dutch electricity network is described as tight and Lithuania is pairing batteries with renewable generation. The projects are Return’s 200 MWh Antares facility in Waddinxveen and European Energy’s 65 MWh battery at a solar park in Anykščiai.
Get backup power and energy gear delivered free with Prime
- Fast, free delivery on millions of items
- Prime Video, Amazon Music and more included
- Member-only deals all year
Return said its 100 MW / 200 MWh Antares standalone battery in Waddinxveen has entered commercial operation ahead of schedule. The facility, in the western Netherlands, is connected directly to grid operator TenneT’s 150 kV high-voltage network. Return said construction, grid connection, testing and commissioning were completed before commercial operation began.
The company credited TenneT, battery integrator Alfen and engineering and technical services firm SPIE Nederland, among other partners, with helping deliver the project. Return’s announcement did not give a precise date for the start of commercial operations or provide details on how the battery will be dispatched or contracted.
In Lithuania, Danish renewable-energy developer European Energy has opened a 25 MW / 65 MWh battery at its Anykščiai energy park. The storage system is co-located with a 78.5 MW solar farm, forming a hybrid facility. European Energy said the battery was connected to Lithuania’s transmission grid in the second quarter of 2026. The site is about 100 kilometers north of Vilnius.
Storage Adds Flexibility to Two Grids
The projects show two different roles for large batteries: adding capacity to a Dutch grid described in the report as tight, and combining storage with solar production in Lithuania. Batteries can store electricity and return it to the grid at another time, but the announcements do not specify the operating strategies, services or market arrangements these particular sites will use.
At Anykščiai, co-location puts the battery alongside a substantial solar facility, creating the potential to shift some electricity output in time. European Energy said the project adds flexibility to its Lithuanian activities. That is the company’s stated purpose; operating data on the battery’s contribution to balancing or renewable integration was not provided.
The combined headline figure of 265 MWh describes energy storage capacity, while 125 MW describes the projects’ power capacity. These are different measures: the MW rating indicates the rate at which systems can charge or discharge, and MWh indicates the amount of energy stored. The figures alone do not establish how long each facility will operate at full output under real-world conditions.
Products Worth Considering

Ring Alarm 8-Piece Home Security System Kit

Ring Alarm 5-Piece Home Security Kit

Levoit Core 400S-P Smart Air Purifier for Large Rooms
As an affiliate, we earn on qualifying purchases.
Two Projects, Different Configurations
Antares is a standalone battery connected to the transmission grid in the Netherlands. European Energy’s Anykščiai installation is instead part of a solar-plus-storage site. The distinction matters because the Lithuanian battery shares a site with renewable generation, while Return’s announcement describes Antares as a standalone project.
European Energy said the Anykščiai site covers about 120 hectares and is expected to generate around 80,000 MWh of renewable electricity annually. That estimate refers to electricity generation at the site, not the battery’s storage capacity. The company also said it operates more than 400 MW of renewable-energy capacity in Lithuania and has a portfolio of approximately 800 MW of solar, wind and storage projects under development there.
The Lithuanian project is European Energy’s first battery-storage project in the Baltics, according to the company. The developer is also expanding storage outside Europe: it began construction in August 2026 on a 40 MW / 80 MWh battery alongside its Mokoan solar farm near Winton, Australia. That project is under construction and is separate from the two facilities now reported in operation.
“A big thank you to all our partners who contributed to bringing Antares from construction to commercial operation. Reaching this milestone ahead of schedule has been a true team effort.”
— Return, in a LinkedIn post
Operating Plans and Grid Effects
The announcements confirm that both batteries have entered operation, but provide limited information about their commercial use. It is not clear what services Antares will provide to TenneT’s grid, how either facility will be dispatched, or what contracts or revenue arrangements apply. The companies did not publish operating results, utilization rates or measured effects on grid congestion and renewable curtailment.
European Energy’s estimate of around 80,000 MWh of annual renewable generation is a forecast, not a reported operating total. The source material also does not specify the battery’s charging mix, round-trip efficiency, or how much solar electricity will be stored rather than exported directly.
Monitoring Commercial Operations
The immediate next step is for both facilities to operate commercially and begin providing their planned grid or energy-market services. Return has said Antares completed commissioning and entered commercial operation, but has not published further information about its dispatch or performance. European Energy has reported that the Anykščiai battery is connected and opened, while its annual generation figure remains an expectation.
Further details from the operators or grid companies could clarify how the batteries are used, how often they charge and discharge, and whether they improve flexibility in their respective networks. The source report does not give a timetable for additional performance updates or name a next project milestone for either site.
Key Questions
How much battery capacity has entered operation?
The two projects total 125 MW of power capacity and 265 MWh of storage capacity: 100 MW / 200 MWh in the Netherlands and 25 MW / 65 MWh in Lithuania.
Where is the Dutch battery and who operates it?
Return’s Antares battery is in Waddinxveen, in the western Netherlands. Return said it has entered commercial operation and connects directly to TenneT’s 150 kV grid.
What makes the Lithuanian project different?
European Energy’s 25 MW / 65 MWh battery is co-located with a 78.5 MW solar farm at the company’s Anykščiai energy park. It is the developer’s first battery project in the Baltics, according to the company.
Does the report show how much the batteries improve the grids?
No measured grid impact or operating data was provided. The companies described the projects’ roles and expected benefits, but dispatch details, utilization and effects on congestion or renewable curtailment remain unclear.